Birse Civils
16 Sep 2010
Birse Civils North West is currently completing a £5.6m Thacka Beck Flood Alleviation
Scheme in Penrith for the Environment Agency.


Work started on site on 16 March 2010 and the scheme is running a month ahead
of schedule with completion planned for November this year. More than 250 homes
and 110 businesses will benefit from the scheme which will significantly reduce
the chance of flooding in the town.
The Sandgate section of culvert installation involved 21m of 2.2m x 1.4m box
culvert being placed in a narrow alleyway between two listed buildings. The construction
methodology had to include for over pumping the existing water flows, as well
as heavily restricted access. This section was originally programmed to take eight
weeks, however work was actually completed within two weeks of continuous operations.
The full works comprise the restoration, replacement and cleaning of 600m of
culvert carrying Thacka Beck under Penrith town centre, together with the creation
of a 76,000 cubic metre flood storage basin upstream. The basin will hold back
flood water and reduce the risk of the culverts overflowing, as well as provide
an enhanced wildlife area.


Environment Agency Project Manager, Mike Harper, said: “We have now completed
the two most technical parts of the scheme at Sandgate and Friargate. At Sandgate,
the width of the passage we were laying the culverts through was barely any wider
than the pre-cast culvert we were installing.
“Through careful planning, Birse Civils were able to carry out the work without
affecting the adjacent buildings and the work was completed swiftly with access
restored promptly to the affected buildings.”




