Site Map | Home
Saturday 4 February 2012
CivilsCoastalNuclear

Environment Agency - Chain of Custody Certified Sites

The table below details the Birse Civils’ sites that are currently engaged in works for the Environment Agency, where our Timber Chain of Custody procedures are required to operate. These procedures are certified under the FSC and PEFC registration schemes.

The table also provides information as to the audit status of each site. These audits ensure that the CoC is being operated effectively and in accordance with our timber procurement policies.
 
This process is agreed and monitored by our auditors BM Trada.
 
Project
Name
Contract No
Project Description                                                                
Contract
Start
Date
Contract
Finish
Date
BM Trada
Audit
Denver Little Eyes
C2345
Stop log and lock gate work
Mar-10
Oct-10
TBC
Dymchurch
C2355
Supply and storage of sheet piles, supply of moulds for precast units, supply of vacuum lifting apparatus, supply of temporary edge protection gabion baskets, manufacture of 280No.precast units
Mar-08
Jul-11
TBC
Gainsborough
Frontages
Phase 2
C2404
Installation of single or double row of ground anchors through existing river walls
Installation of structural steel waling beams
Tidal working for low level anchors
Interface with public / private landowners for access
Monitoring of existing structures during works
Protection and / or removal of high quality landscaped areas and private gardens in order to gain access
Protection of trees subject to TPO’s
Nov-08
Jul-10
TBC
Stallingborough
Sea Defences
C2418
Improvement works to the existing open stane asphalt revetment at Stallinborough
Apr-09
Oct-09
TBC
Penrith
C2423
Site Clearance: Felling of a number of trees and low lying shrub clearance in preparation for future works
Mar-10
TBC
TBC
East Holton
C2429
Improvement works to the existing tidal defences at Halton Marshes, North Lincolnshire
Feb-09
Mar-10
TBC
Swinefleet
C2478
Flood defence works consisting of earth bund embankment and piling. Toe piling in river to be carried out from barges.
Jun-09
May-10
TBC
Dartford Creek 2
C2509
Design, manufacture, testing, installation and commissioning of the replacement mechanical and hydraulic drive, electrical and control systems, design and implementation of non-priority H&S improvements and recoating of the barrier gates for the Dartford Creek tidal barrier.
Feb-10
Aug-10
TBC
Gunness
Flood Bank
Improvement
C2520
Installation of 3.6km of 2.5m long plastic piles on the existing flood bank near Gunness.  Works are adjacent to the River Trent which has tidal flows. Landscaping works upon completion of piling.
Dec-09
Jun-10
TBC
Newmans Sluice
Gates
C2523
The replacement of 4 power operated vertical lift gates at Newmans Sluice.  Associated remediation of channel bed scour downstream of the sluice, improvements to the adjacent access track and offsite environmental enhancement works.
Mar-10
Oct-10
TBC
Morpeth Dock
Pumping Station
C2526
Demolition of dock building and infilling of dock.
Mar-10
Mar-10
TBC
Purls Bridge
emergency repairs
C2533
Emergency repairs to failed section of existing river bank including earthworks, sheet piling and capping beam works
Feb-10
May-10
TBC
Donna Nook
Managed
Realignment
C2541
Flood defence works consisting of earth bund embankment and piling. Toe piling in river to be carried out from barges.
Apr-10
Jun -11
TBC
BAP Habitat
(Beam Park)
C2543
Earth movement and bank shaping of the River Beam and Wantz Stream with vegetation creation and enhancement to improve the park environment
Jun-10
Jun-10
TBC
Tilbury Flood
Alleviation
C2548
The raising of the crest levels of the existing earth embankments, ditch realignment, concrete wall.
Apr-10
Jul-10
TBC
Dog in a Doublet
C2551
Refurbishment of existing sluice gate structure including replacement of motors and ropes to gates and control systems, installation of CCTV, navigation lights, cable ducts and boxes, cleaning and repainting of gates and support structure, removal, refurbishment and reinstallation of gearboxes and concrete repairs to structure. Access road, crane pad, earthworks and fencing.
Apr-09
Jan-11
TBC
Lincshore
C2552
Dredging and beach recharge on an annual basis.
May-10
Dec-10
TBC
Arklyn Flood
Alleviation
C2554
River bank enhancements and flood alleviation improvements consisting of sheet piles, precast concrete walls and in-situ concrete walls - all to maintain and improve flood protection for private properties
Apr-11
Dec-11
TBC
Hayling Islands
& West Wittering
C2557
Design, value engineering and buildability advice during ECI phase.
Oct-09
Jul-10
TBC
Soham Lode
Seepage Remedial
Works
C2571
Liner to existing watercourse
Sep-10
Jan-11
TBC
Clwyd Embankment
C2573
Raising of existing earth flood prevention embankments on both banks of River Clwyd, existing cycleway, existing slipways and concrete retaining walls to new levels.
Jul-10
Nov-10
TBC
Brough FAS
C2574
Extension of an existing sheet piled wall by approximately 500m along the landward crest of an existing flood embankment. Construction of approximately 1500m of 3.5m high earth embankment. Outfall improvements.
Jul-10
Feb-11
TBC
Western Drain FAS
C2579
Extension of an existing sheet piled wall by approximately 500m along the landward crest of an existing flood embankment. Construction of approximately 1500m of 3.5m high earth embankment. Outfall improvements.
Jul-10
Dec-10
TBC
National Framework
contractors 2
C2586
Installation of 2No 600mm dia river outfall drains between drainage ditches and the River Severn.
Aug-10
Nov-10
TBC
Wicken Fen WLMP
C2587
Supply and installation of a Wind Pump Tower, two sump chambers to the north and south of Wicken Lode, interconnecting concrete pipe and water supply ditch.
Aug-10
Nov-10
TBC
Lincshore Beach
Nourishment
C2592
Beach nourishment and other coastal works at locations between Mabelthorpe and Skegness.
Oct-10
Oct-14
TBC
Oxford STM
Phase 2
C2599
Hinskey dredging. Silt removal and in-channel works. Bank cut and tree clearance. Seacourt and Bulstake Stream culverts. Four small culvert units installed in existing embankment area.
Oct-10
Apr-10
TBC
Fiskerton Sluice
Refurbishment
C2602
Construction of a new downstream cut off and filling of a large void under the downstream apron. Removal and repainting of gates. New tracks and seals. Repair of piers and wing walls. New access stairs and decking. New actuators and electrical system. New bulkhead gates. Installation of a fish pass.
Oct-10
Feb-11
TBC   
 
 
 
 
 
Cone Pill, Lydney
C2586
Installation of river outfall drains between drainage ditches and River Severn
Aug-10
Oct-10
TBC
Newport FAS
C2512
Replace existing flood wall on the River Usk near Newport
Jan-11
Mar-11
TBC
Burringham Emergency Slip Repairs
C2621
Emergency repairs to slipway on River Trent near Burringham in Lincolnshire
Jan-11
Mar-11
TBC
Redcar
C2622
Flood alleviation and landscape enhancement works in Redcar
Jan-11
Jan-13
TBC
Prestbury FAS
C2625
Installation of flood relief culverts and bypass ditches near Cheltenham
Feb-11
Jun-11
TBC
Afon Ganol
C2630
Replacement of tidal outfall structures
Feb-11
Mar-11
TBC
Thetford Sluices
C2672
Replacement of M&E sluice equipment
Jul-11
Sept-11
TBC
Thames Tidal Frontages
C2644
Flood defence works at various Thames tidal locations   
Mar-11
Dec-12
TBC
Reconditioning local levy and associated works
C2689
Repair and replacement of local levy, water resources and other works at various locations in the Eastern region
Aug-11
Mar-12
TBC

Our public product list is as presented below; our ‘product’ does not fit within the categories presented in the FSC standard addendums:

  • Addendum to FSC Standard FSC-STD-40-004 – FSC Product Classification FSC-STD-40-004a (Version 1-0) EN
  • Addendum to FSC Standard FSC-STD-40-004 – FSC Species Terminology FSC-STD-40-004b (Version 1-0) EN
In order to comply as best as possible with these FSC requirements our ‘project type’ presented can be considered our ‘product categorisation’ that is publicly available in line with the standard addendums mentioned above.
 
Last updated: December 2010